Timeschedule | Pert Chart
 
 

TIMESCHEDULE OF PROJECT

ACTIVITY DURATION (in days)
START
FINISH
1.
Contract
1
01/11/95
01/11/95
2.
Topographical work
15
02/02/95
02/22/95
3.
Research drilling
1
05/01/95
05/01/95
4.
Landfill behind the bridge
1
05/15/95
05/15/95
5.
Breakwater head C
350
06/10/96
10/10/97
6.
Construction of breakwater head C core with riprap
100
06/10/96
10/25/96
7.
Protection of breakwater head C with artificial blocks (Category A')
100
01/06/97
05/23/97
8.
Protection of breakwater head C with artificial blocks (Category B')
100
05/26/97
10/10/97
9.
Connecting bridge
285
09/04/95
10/04/96
10.
Vibro-compacted method (bridge area)
90
09/04/95
01/05/96
11.
Confirmation of vibro-compacted method (bridge area)
90
09/11/95
01/12/96
12.
Excavation for foundation of bridge
90
09/18/95
01/19/96
13.
Reforming the sea bottom for the foundation of bridge
90
09/25/95
01/26/96
14.
Bridge Deck
60
01/29/96
04/19/96
15.
Construction of bridge superstructure
120
04/22/96
10/04/96
16.
Riff landfills with dredges
293
09/18/95
10/30/96
17.
Landfills between Caissons and marinas quay-walls
400
09/18/95
03/28/97
18.
Artificial blocks (A. B.)
615
08/07/95
12/12/97
19.
Excavation of sea bottom ( A.B. area)
70
10/23/95
01/26/96
20.
Cleansing of sea bottom ( A.B. area) with gravel
70
10/30/95
02/02/96
21.
Cleansing of sea bottom ( A.B. area) with riprap
70
11/13/95
02/16/96
22.
Construction of A.B.
450
08/07/95
04/25/97
23.
Transport -Anchor-Casting of A.B.
450
11/20/95
08/08/97
24.
Construction of relieving prism (Marinas quay-walls)
400
02/26/96
09/05/97
25.
Construction of filter (Marinas quay-walls)
400
03/04/96
09/12/97
26.
Superstructure landfills
200
01/20/97
10/24/97
27. Superstructure construction
200
02/10/97 11/14/97
28.
Superstructure equipment
200
03/10/97
12/12/97

   