FINANCIAL DATA

A. Port construction  
  Excavations and Landfills: 267.215.000 GRD
  Quay Walls: 1.185.689.500 GRD
  Reinforced Concrete Works: 1.598.505.000 GRD
  Projects for the improvement of the foundation ground: 142.500.000 GRD
  Architectural formations of superstructure: 41.204.500 GRD
 
  Total: 3.235.114.000 GRD
B. Technical Studies: 323.342.436 GRD
C. Geotechnical Study: 8.348.158 GRD
Total Cost of Works: 3.566.804.594 GRD
General Expenses and Contractor Profit: 640.024.827 GRD
Unexpected Expenses: 73.277.156 GRD
Review: 142.672.184 GRD
VAT: 575.221.239 GRD

Total project cost: 5.000.000.000 GRD
Note: 340.75 GRD = 1 €