Timeschedule | Pert Chart
 
 

TIMESCHEDULE OF PROJECT

ACTIVITY DURATION (in days)
START
FINISH
29.
Cellular Blocks (Caisson)
675
09/04/95
04/03/98
30.
Vibro-compacted method
95
09/04/95
01/12/96
31.
Geotechnical works - Confirmation of vibro-compacted method
90
09/18/95
01/19/96
32.
Construction of the first caisson
60
10/19/95
01/10/96
33.
Excavation of sea bottom (caisson area)
240
09/25/95
08/23/96
34.
Base riprap
240
10/02/95
08/30/96
35.
Construction of 22 caisson
250
01/25/96
01/08/97
36.
Construction of 24 caisson
260
01/09/97
01/07/98
37.
Transport -Anchor-Casting
500
03/21/96
02/18/98
38.
Construction of relieving prism (caisson)
500
03/28/96
02/25/98
39.
Construction of filter (caisson)
500
04/01/96
02/27/98
40.
Paving of cellular boxes
500
04/04/96
03/04/98
41.
Completion of superstructures landfills
200
06/02/97
03/06/98
42.
Superstructure construction
200
06/23/97
03/27/98
43.
Superstructure equipment
200
06/30/97
04/03/98
44.
Covering of cellular boxes
50
04/06/98
06/12/98
45.
Architectural modulation
30
05/11/98
06/19/98
46.
Construction of roads
30
05/11/98
06/19/98
47.
Remaining works
60
04/06/98
06/26/98
48.
Road Asphalting
25
05/25/98
06/26/98
49.
End of works
1
06/29/98
06/29/98

   